A quiet two-lane road curves through mostly bare birches and evergreen trees beside a calm Northern Michigan river in November.

Grand Traverse County's Road Season Ends When the Asphalt Plants Do

On Thursday, Nov. 5, Grand Traverse County Road Commission crews pulled the cones off Hammond Road and danced in a video celebrating the reopening, as The Ticker reported. The Hammond job had dragged on for months. In late October, road commission manager Dan Watkins told 9&10 News that crews had hit underground utilities no one knew were there, plus water problems. Because Hammond carries so much traffic, the final pavement runs more than 5 inches thick, compared with about 3.5 inches on a standard road. Two pavers worked side by side to lay it.

Hammond was the first of a group of reopenings packed into the same few weeks. The calendar drives that timing, and it is why South Airport Road, which carried Beitner's detour all year, is losing a lane right as Beitner is due back.

Why Everything Finishes at Once

Michigan's asphalt plants are expected to close by mid-November. That is why the Beitner Road bridge contract carried a Nov. 13 completion date when the Michigan Department of Transportation let it this summer, Watkins told the Record-Eagle. The same cutoff applies to every paving job in the county, so county, city and state projects are all racing the same clock.

The weather has helped. Watkins told 9&10 News the dry fall was ideal for paving, and that in some years crews would already be seeing snow by late October. He also summed up the year this way:

"We know this has been an extremely rough year. We all live here. So we're right there with you and we're very excited to get these projects done and back open."

That quote comes from his 9&10 News interview. In that interview, he described the year as a major winter storm, then high water, then construction, with the city, county and state all running projects at the same time.

The Bridge That Set This Year's Traffic Pattern

Most of this year's commute trouble goes back to one Tuesday in April. During the statewide flooding, Beitner Road's dual-culvert crossing collapsed into the Boardman-Ottaway River, and The Ticker reported in April that the road would likely be out at least six months. By May, Grand Traverse County's preliminary flood damage estimate had reached $21.2 million, with $9.3 million of it in road damage. The Ticker named Beitner and the Brown Bridge Road crossing as the two most significant repair projects.

With Beitner gone, its traffic shifted to Cass and South Airport roads. The road commission put in a temporary signal at Cass and Hartman and started work on another at Hartman and US-31 to handle the extra cars. The Record-Eagle reported that more than 15,000 drivers will use the new bridge once it opens, which shows how much traffic those detour roads have been carrying since spring.

The replacement bridge is a single concrete span built by Grand Haven-based Anlaan Corporation under a contract of about $3.7 million. Crews poured the deck in late October. Its six beams were built in Indiana and served as their own trailers on the trip north. Watkins told 9&10 News that one tight turn or crash on the way could have set the job back by months. All six arrived in good shape. After the deck pour, the road commission said it expected the bridge to open sometime in November. That is well ahead of the Christmas target the agency gave in July and the "end of the year" it had been saying all along.

The Bypass Takes the Last Hit

As Beitner nears the finish, South Airport Road, its main stand-in all year, has its own lane closure. Garfield Township is replacing about 1,400 feet of sewer main from near Logan's Landing up the hill to the Park Drive intersection. The work comes after the old undersized pipe under South Airport cracked and leaked sewage this summer. Contractor Team Elmer's was set to start Monday, Nov. 9, and the project is expected to take three weeks, according to The Ticker.

The traffic changes on a road that carries about 60,000 cars a day:

  • Westbound South Airport is down to one lane between Park Drive and west of Logan's Landing, and may be stopped entirely at times so trucks and equipment can move through.
  • Both eastbound lanes stay open, and so does Logan's Landing.
  • A short section of Park Drive is closed near South Airport. Drivers coming from Woodmere Avenue can take Park up to the Gardner White driveway, but they can't turn onto South Airport from Park.
  • The short north-south connector that links both sides of South Airport near Verizon is closed.

The township could not wait until spring. Officials said that delaying the project could be catastrophic if the pipe failed again over the winter. South Airport would be shut down with no way to finish asphalt repairs in the cold until spring. The new main also has double the old one's capacity, going from 700 gallons per minute at peak to 1,400.

The pipe will run under county-owned Medalie Park instead of the road right-of-way. The Grand Traverse County Road Commission asked for that so the main won't have to be torn out when the South Airport crossing over the river is rebuilt, possibly with the bridge raised out of the floodplain. Because Medalie Park has received DNR grant money, the county needed written DNR approval for the easement, The Ticker reported. That approval came in the day after county commissioners voted. The pipe is going in with trenchless methods, and the boring pits sit off-site, so the park surface isn't disturbed.

Beitner's reopening could ease some of the South Airport squeeze. Watkins told The Ticker, though, that if the two timelines overlap at all, it would likely be only in the final week of the South Airport work.

The Order Things Come Back

Here is how the rest of the month lines up, based on the latest timelines from the agencies running each job:

  1. Hammond Road reopened Nov. 5. The road work was paired with a Safe Routes to School path that adds 1.6 miles of walking and biking trail, along with new signals at Hammond and Three Mile. Watkins told 9&10 News that people were already using the path before paving was finished.
  2. US-31 through Grawn and Interlochen has two-way traffic back along the whole corridor, and MDOT says it is on schedule to finish by Nov. 15. Until then, expect occasional shoulder or lane closures for final touches. The $32.5 million project rebuilt and widened 7.8 miles from Sullivan Road to Reynolds Road. It added center left-turn lanes, wider shoulders and a roundabout at South Long Lake Road and J. Maddy Parkway.
  3. Beitner Road bridge is expected to open sometime in November.
  4. South Airport Road gets its westbound lanes back when the sewer work wraps up, about three weeks after the Nov. 9 start. That puts it close to the end of the month, through Thanksgiving week.

The road commission also scheduled two one-day culvert replacements with detours, on South Long Lake Road on Monday, Nov. 9, and on Karlin Road on Tuesday, Nov. 10, weather permitting.

What the Flood Pushed Into 2027

The Beitner collapse also changed next year's construction plans. The Cass Road rebuild from South Airport Road to Robbins Bridge was moved from 2026 to 2027 because Cass was carrying Beitner's detour traffic. That project includes a new signal and dual turn lanes at Cass and South Airport, the same intersection that has been busiest all year, The Ticker reported.

A few other projects are also carrying into next year:

  • Bluff Road stays closed for a half-mile between Boursaw and Blue Water roads. The road commission is seeking design proposals to stabilize the slope and shoreline before rebuilding the road.
  • Parking Lot B downtown stays closed for the Sara Hardy Downtown Farmers Market Pavilion project, which the City of Traverse City expects to finish in spring 2027, according to its October Bay Brief.
  • The Brown Bridge Quiet Area expansion and Spring Lake Trailhead are in design, with construction expected to start in spring 2027. The plans include parking, restrooms, an accessible trail and a Spring Lake viewing platform, per the city's September Bay Brief.

Road commissioners have also agreed to look at the other Boardman River crossings that use culverts and possibly plan to replace them with span bridges over time. That is the same design change Beitner is getting now.

If you're planning a move and want to know how corridors like South Airport, Cass and Beitner affect daily drive times in different parts of the county, Traverse City Real Estate can go over the routes with you as part of your search. Schedule a Consultation, and we'll start with the roads you'd use every day.

Furnished entryway with a white front door, gray sofa, framed artwork, and snowy views through the windows.

Let's Connect

We provide a first-class client experience that produces life-changing results without sacrificing integrity or a smile! Reach out now to get started with your real estate goals.

Follow Us on Instagram